Agenda
- Operations:
- Run 59 progress:
- Another slow cooldown to base. This run and Run 58, the two runs using the Soudan tower. (Why would this be different?)
- Run 59 (G106a) plan:
- second HV attempt
- phonon collection efficiency versus mu-metal shield height. (Scheduled to report on this July 22)
- more data for position reconstruction studies - multiple Am sources in different positions
- Possibly test DCRC RevD with adapter board from UCB.
- May want to study phonon noise more.
- Future runs:
- 6“ contact-free (aka vacuum interface)
- Queen's visit in 2 weeks, Run 59 (G106a) will be in progress
Sidewall source ?- Theoretically, Ge-iZIP prototype detector arrives from TAMU in
OctoberSeptember. Supposed to test this and Ge-HV prototype before CD2 early next year.
- HPGe configuration (purpose is for neutron capture/recoil study, want to trigger iZIP on HPGe gammas)
- DAQ and data pipe
- Data storage and backup:
- Still need to back up Run 58 to SLAC
- Need to set up a system for copying incoming data
- Code education: should try to find time to continue studying this (Matt, David?, Nick?, Allison?)
- Processing and Analysis
- Run 58 (USD1): Finally found some peaks, poor charge collection efficiency
- Progress in NSOF development for reprocessing
- What should we plan to publish?
- Physics
- Low-energy NR peaks from neutron capture in Ge