Agenda
- Operations:
- Run 59 progress:
- more mu-metal tests, more confusing behavior
- Run 59 (G106a) other tasks:
- second HV attempt
- more data for position reconstruction studies - multiple Am sources in different positions
- Possibly test DCRC RevD with adapter board from UCB.
- May want to study phonon noise more.
- Future runs:
- 6“ contact-free (aka vacuum interface) - scheduling will be challenging
Sidewall source ?- HV prototype tests for project
- Now they want us to do two of these by end of year
- Expected to get the first by September although Paul thinks maybe October
- We will want to build the second HV board to switch bias/readout polarity (Nick will order components and build it)
- DAQ and data pipe
- Data storage and backup:
- Run 58 raw data is backed up at SLAC
- Need to set up a system for copying incoming data
- Need to clean up vuk1/vuk2 before they are retired
- Code education: Nick and Allison are learning about processing code. Matt&David should work on this too.
- Processing and Analysis
- Run 58 (USD1): Take another look in prep for R&D meeting
- What should we plan to publish?
- Things not working…
- Update on IVC leak to bath
- Working around the bad charge channel
- attempting mu-metal analysis using phonon z-info instead of charge
- noise from channel causes processing failure, adjusting processing, also attempting running with FETs off which reduces noise
- Physics
- Low-energy NR peaks from neutron capture in Ge