Agenda
- Operations:
- Run 56 (the current run): Run 56 Summary
- Tests with inverting half the phonon pulses
- Ending run
- Next run: probably G114 (the other iZIPv6) for HV attempt, maybe other studies, no internal source
- Note from Paul B: this is the first AJA detector, and there are some concerns re “step coverage” and continuity. If Rn's are found to be too high (say, >1.5 Ω) then we should probably immediately deem this detector “bad” in terms of phonons at least. Could still try to test HV characteristics with charge only.
- Future runs: SD crystal, 6“ crystals, sidewall source, G106a with no-internal-source
- Plan to demount G101b, ship it to TAMU, use its housing for SD crystal, need to wirebond
- need to learn more about the purpose of the sidewall source detector, aka G55
- DAQ and data pipe
- Data storage and backup issues
- Phonon trace discontinuities
- Analysis: updates and planning