UMN CDMS Wiki archive
start › cdms › k100 › run_diary › 20221010

2022/10/10 (Monday)

Previous Day

  • Lab in-personnel: Matt
Status Run 76 in progress
Setup Cables 2/3/1 → diverter/nothing/nothing → Side2-readout HV CONN 1/3/2 → HV 1(L)/2(R) → DCRC50(3)/DCRC55(1), DCRC33(2)→HV control, NaI trigger signal → DCRCX(4)
Lead/poly shield fully assembled. Boron-filled socks covering NaI detectors.
PuBe source behind lead wall on West side of lead/poly shield.
NaI trigger window: 7.6-11.2 MeV
warmed up yesterday for 13th 5K pumpout. But didn't start pumping out the IVC yet.
1120 MC/1KPot/Sorb = 5.31/5.58/7.0 K.
1120 Unplug DCRCs 1&3
1120 Check pressure in IVC: 0.16 ubar.
1120 Start pumping out IVC with turbo pump
1235 MC = 7.54 K
1235 Turbo on IVC = 2.2 ubar. With Turbo valve out for 1 minute, IVC = 46 nbar
interestingly with Turbo valve out for several minutes, MC temperature starts falling rather than rising. I may have expected the pressure to already be low enough to break the thermal link to the bath. But it looks like active pumping is necessary to keep the MC warming.
after about 20 minutes the MC temperature kinda flattened out
1255 Pry the stripline elbow up by wedging a screwdriver between the knurled knobs and put a couple of washers in the gap to hold it up. Try pushing some vacuum grease into the gap, a little more effort than last time - cut the wooden end of a swab down a bit into a flat shape to try to push the grease upward into the gap between the knurled knob and the stripline tube. Do this all the way around. Then remove the washers and push the elbow down again.
1405 Restart turbo-pumping IVC
1500 MC/1Kpot/Sorb = 10.10/>7/9.8 K
Turn off MC and Still heaters
1538 Begin LHe transfer @ MB = 34.8%
1545 Fill LN2 cold trap bath
1623 End LHe transfer @ MB = 95.6%

Next Day