| 1206 | Check contents of warm LN2 Trap 2: 4.9 mbar (5.4 on G1). Pump it out with the scroll pump. |
| 1212 | G1 = 1.5 mbar and stable, stop pumping on Trap 2 |
| 1213 | Insert LN2 cold trap 2 and begin filling cold trap dewar with LN2 |
| 1222 | Begin cryocleaning mixture through cold trap 2 following the procedure in procedure:cryoclean_mixture |
| 1225 | Open V6 to 12.0% to restart flow |
| 1231 | Open V6 to 12.2% to restart flow |
| 1240 | Open V6 to 12.3% to restart flow |
| 1333 | End cryocleaning mixture through trap 2. Pump mixture to dump |
| 1358 | P1 = 0.007 mbar, G1 = 2.0 mbar and stable. Close all valves and turn off 3He pump, leaving 713.8 mbar in dump |
| 1401 | Remove cold trap 2 from the LN2 bath to warm up overnight |