from current P6 project schedule

start finish
HV#2, run 61 2016 Oct 10 2016 Dec 16 (BL)
HV#4, SiHV prototype 2017 Jan 3 or 19 2017 Mar 6 or 19
Design cryogenic tails 2016 Oct 3 2017 Apr 22
Readout cables feedthrough & heatsink design 2017 Feb 8 (BL) 2017 Mar 21 (BL)
Installation fixture ? ?
Heat load test run with tails and tower 2017 Jul 12 2017 Jul 19
Heat load test run with readout cables 2017 Aug 2 2017 Aug 16
Detector testing readiness review 2017 Aug 16 2017 Aug 29
HV#5 GeHV preproduction 2017 Aug 30
(informal sched had this starting in May)
2017 Nov 20
… … …