from current P6 project schedule
| start | finish | |
|---|---|---|
| HV#2, run 61 | 2016 Oct 10 | 2016 Dec 16 (BL) |
| HV#4, SiHV prototype | 2017 Jan 3 or 19 | 2017 Mar 6 or 19 |
| Design cryogenic tails | 2016 Oct 3 | 2017 Apr 22 |
| Readout cables feedthrough & heatsink design | 2017 Feb 8 (BL) | 2017 Mar 21 (BL) |
| Installation fixture | ? | ? |
| Heat load test run with tails and tower | 2017 Jul 12 | 2017 Jul 19 |
| Heat load test run with readout cables | 2017 Aug 2 | 2017 Aug 16 |
| Detector testing readiness review | 2017 Aug 16 | 2017 Aug 29 |
| HV#5 GeHV preproduction | 2017 Aug 30 (informal sched had this starting in May) | 2017 Nov 20 |
| … | … | … |