To-Do List for K100

  • Labview DAQ stability issues
    • Fix software freezing
    • Determine consistent event rates during run
    • Side note- LabView software station?
  • DCRC boards
    • Coordination with FNAL for establishing simultaneous use of boards
    • Interface boards
      • Hassan
  • Hardware for 100 mm tests (to take place in 2012)
    • Adapter plate (make)
    • Source holder (make)
      • SLAC
    • Side-Coaxes(acquire)
      • Position 1, Position 4
    • SQUET card (acquire)
    • Stripline
    • New switch and ethernet card
  • Tower face problems (two sides)
  • Automation of DAQ-CDMSBATS interface
    • Reduce time in obtaining reduced quantities (RQs)
    • Determine steps to solve this issue - need heavy contact with Jeter
    • Jianjie, Allison
  • Microscope for clean room
    • ask Stein about magnifier
  • Digital camera for lab
  • Alex
  • LN2 scale
    • Allison
  • K100 manual revision
    • Rough copy by 2011/12/12
    • Roxanne, Allison, Alex
  • Side-coax replacement
    • Design/build by end of semester
    • Test next year
    • David
  • Ib-Is measurement through LabView
    • Alex
  • K-40 source studies
    • Allison
  • Am-241 source holder
    • Extract source from holder
    • Fabricate new source holder - install
    • Jianjie
  • Gd-loaded polyethylene tests
  • iZIP surface event rejection tests
    • Need to establish neutron-gamma rejection
    • Will need simulation work
    • Thinking ahead, will need beta source
    • Vuk
  • Lab library
    • Roxanne, Hassan
  • Get Windows machine established