| 0200 | Tower installation complete. IVC sealed. |
| 0216 | Start pumping IVC and Dewar. Dewar pressure is >3e-2bar before pumping. |
| 1320 | Stop pumping dewar. |
| | Conduct helium leak check. Leak rate 5.5E-9 mbar l/s: fine. |
| 1400 | Conduct quick electrical check: everything looks good. |
| | Raise dewar. |
| 1500 | Overpressure main bath with He gas. Helium leak rate 7E-9 mbar l/s: good enough. |
| | Evacuate 1 K pot. |
| | Fill IVC with 5.4 mbar N2 exchange gas. |
| 1600 | Begin nitrogen transfer. |
| 1800 | Level meter resistance 1.32 kΩ. Stop nitrogen transfer. |
| 1830 | Stop evacuating mixing chamber lines. Pressure of G2 615 mbar. |
| | Start cryocleaning mixture through cold trap 2. Valve 6 open 13.8%. |