- Lab Update - Run 76 in progress
- recalibrating NaI detectors using PuBe
- looking at data series where HV started at -200V and then was ramped down. HV Calibration test. Somewhat confusing results.
- need to check recent series for stability.
- Priority Updates
- General Updates
- Himangshu
- Shubham
- Tower 1 and Tower 2 (with detectors) have been tested, packed up, and stored in UG tunnel at Stanford.
- Detector stacking for Tower 3 will be done soon, and will be installed in the Bluefors for testing.
- We have started assembling Tower 4 body.
- Jack
- Derek
- Zach
- Michael
- Scott
- Giulia
- Giovanna
- Nikki
- Pramod
- Fun Update