Run 76 beginning. Tried to finish installation Friday but had trouble with a short: a phonon channel wire was shorted to the 4K stage of the tower (only the 4K stage, so we missed this at bench test)
Came in Saturday, fixed short (not sure how), finished installation and started pumping out IVC
Electrical checks today - all good except for one motor coil reads open (one of the X-motor coils). Decided we need to push forward - we won't have a fully functional source mover but we can test the Y-motor
Plan is LN2 today, LHe tomorrow, start circulation Wednesday, see pulses Thursday. Assuming no leaks or blockages or new shorts arise.